As Harte Gold (HRT.to) decided to bury its disaster NR late on Friday evening…

….it’s only correct that IKN puts it right in front of your face on Monday morning, all special and ready for the opening bell.

Harte Gold Provides Third Quarter Update and Guidance for 2019

TORONTO, Nov. 01, 2019 (GLOBE NEWSWIRE) — HARTE GOLD CORP.
(“Harte Gold” or the “Company”) (TSX: HRT / OTC: HRTFF / Frankfurt:
H4O) provided the following operating results for the third quarter (“Q3
2019”) ended September 30, 2019.
Highlights
  • Mined tonnage increased 9% quarter over quarter.  The mill is now being fed 100% run of mine (“ROM”) ore
  • Stope
    production and sequencing was lower than expected due to continued
    start-up delays of the paste fill plant and lower than planned
    development rates
  • Underground infrastructure and contractor performance issues driving the quarter are being addressed
  • A temporary solution for the paste fill plant has been implemented and will continue in the short term
  • Gold production was 6,069 ounces for the quarter.  For the last nine months, Harte Gold produced 19,138 ounces
  • Quarterly
    results when compared to the Feasibility Study were below target. 
    Based on results to-date, full year 2019 guidance has been adjusted to
    24,000 to 26,000 ounces at an AISC of US$2,000 to US$2,200 per ounce. 
    Previous guidance was 39,200 ounces at an AISC of US$1,300 to US$1,350
    per ounce.
  • A life of mine plan for 2020 is being prepared and further guidance and will be provided when available
Operating Metrics, Q3 2019
      Q3 Comparison to Q2 Q3 Comparison to
Feasibility Plan
 
  Q3
September
30, 2019
  Q2
June 30,
2019
Q3 vs. Q2   Feasibility
Plan
Q3 vs.
Feasibility
Plan
 
Ore mined (tonnes) 46,235   42,601 9 %   58,100 (20%)  
Ore processed (tonnes) 56,558   53,216 6 %   58,100 (3%)  
Average daily throughput (tpd) 628   591 6 %   646 (3%)  
Processed grade (g/t) 3.64   4.89 (25%)   5.96 (39%)  
Recovery (%) 92%   93% (0%)   96% (3%)  
Gold ounces produced 6,069   7,754 (22%)   10,600 (43%)  

Mine Production Ramp Up Overview

  • The Company is mining from areas developed at the Sugar Zone North and South ramps
  • Mill
    feed grade decreased due to a shortage of development of higher-grade
    stoping areas, which resulted in a larger contribution of lower grade
    development ore as the primary mill feed
  • Development
    delays and paste plant start-up issues also affected overall stope
    sequencing, which resulted in the Company mining off plan
  • To address challenges in Q3, the following steps have been taken:
    • Mine
      performance was addressed with the mining contractor and necessary
      actions are being taken to ensure adequate staffing and broader
      recruitment efforts
    • The paste plant is expected to be
      operational by year-end.  Critical components are being installed.  The
      Company will provide further updates on start-up of the paste plant as
      they become available
    • Mine infrastructure to support rock fill has been developed and will mitigate delays in operation of the paste fill plant
    • Improvements are underway to expand compressed air capacity, expected to increase the rate at which stopes can be developed
Adjusted 2019 Production and Guidance
Gold
production in the first nine months of 2019 was 19,138 ounces.  Due to
issues around mine development and stope availability in Q3, the Company
expects fourth quarter production to be in the range of 5,000 to 7,000
ounces.  Accordingly, full year 2019 production guidance has been
adjusted from 39,200 ounces per original guidance, to 24,000 to 26,000
ounces.
While operating costs were stabilized
in Q3, as a result of lower production for the year and higher costs in
the first half, annual AISC guidance has been modified and is expected
to be in the range of US$2,000 to US$2,200 per ounce, from original
guidance of US$1,300 to US$1,350 per ounce.  Further information on
operating costs will be provided when the Company files its Q3
financials.
2020 Life of Mine Plan and Financial Budget
The
Company is currently updating its life of mine plan and preparing a
2020 budget.  The Company will provide further guidance for 2020 at that
time.
For further information, please contact:
Stephen G. Roman                                                                                         
Chairman and Interim CEO                                                                         
Tel: 416-368-0999                                                                                           
Email: sgr@hartegold.com                                                                           
Shawn Howarth
Vice President, Corporate Development
Tel: 416-368-0999
E-mail: sh@hartegold.com