Harte Gold Provides Third Quarter Update and Guidance for 2019
TORONTO, Nov. 01, 2019 (GLOBE NEWSWIRE) — HARTE GOLD CORP.
(“Harte Gold” or the “Company”) (TSX: HRT / OTC: HRTFF / Frankfurt:
H4O) provided the following operating results for the third quarter (“Q3
2019”) ended September 30, 2019.
(“Harte Gold” or the “Company”) (TSX: HRT / OTC: HRTFF / Frankfurt:
H4O) provided the following operating results for the third quarter (“Q3
2019”) ended September 30, 2019.
Highlights
- Mined tonnage increased 9% quarter over quarter. The mill is now being fed 100% run of mine (“ROM”) ore
- Stope
production and sequencing was lower than expected due to continued
start-up delays of the paste fill plant and lower than planned
development rates - Underground infrastructure and contractor performance issues driving the quarter are being addressed
- A temporary solution for the paste fill plant has been implemented and will continue in the short term
- Gold production was 6,069 ounces for the quarter. For the last nine months, Harte Gold produced 19,138 ounces
- Quarterly
results when compared to the Feasibility Study were below target.
Based on results to-date, full year 2019 guidance has been adjusted to
24,000 to 26,000 ounces at an AISC of US$2,000 to US$2,200 per ounce.
Previous guidance was 39,200 ounces at an AISC of US$1,300 to US$1,350
per ounce. - A life of mine plan for 2020 is being prepared and further guidance and will be provided when available
Operating Metrics, Q3 2019
| Q3 Comparison to Q2 | Q3 Comparison to Feasibility Plan |
||||||||
| Q3 September 30, 2019 |
Q2 June 30, 2019 |
Q3 vs. Q2 | Feasibility Plan |
Q3 vs. Feasibility Plan |
|||||
| Ore mined (tonnes) | 46,235 | 42,601 | 9 % | 58,100 | (20%) | ||||
| Ore processed (tonnes) | 56,558 | 53,216 | 6 % | 58,100 | (3%) | ||||
| Average daily throughput (tpd) | 628 | 591 | 6 % | 646 | (3%) | ||||
| Processed grade (g/t) | 3.64 | 4.89 | (25%) | 5.96 | (39%) | ||||
| Recovery (%) | 92% | 93% | (0%) | 96% | (3%) | ||||
| Gold ounces produced | 6,069 | 7,754 | (22%) | 10,600 | (43%) | ||||
Mine Production Ramp Up Overview
- The Company is mining from areas developed at the Sugar Zone North and South ramps
- Mill
feed grade decreased due to a shortage of development of higher-grade
stoping areas, which resulted in a larger contribution of lower grade
development ore as the primary mill feed - Development
delays and paste plant start-up issues also affected overall stope
sequencing, which resulted in the Company mining off plan - To address challenges in Q3, the following steps have been taken:
- Mine
performance was addressed with the mining contractor and necessary
actions are being taken to ensure adequate staffing and broader
recruitment efforts - The paste plant is expected to be
operational by year-end. Critical components are being installed. The
Company will provide further updates on start-up of the paste plant as
they become available - Mine infrastructure to support rock fill has been developed and will mitigate delays in operation of the paste fill plant
- Improvements are underway to expand compressed air capacity, expected to increase the rate at which stopes can be developed
- Mine
Adjusted 2019 Production and Guidance
Gold
production in the first nine months of 2019 was 19,138 ounces. Due to
issues around mine development and stope availability in Q3, the Company
expects fourth quarter production to be in the range of 5,000 to 7,000
ounces. Accordingly, full year 2019 production guidance has been
adjusted from 39,200 ounces per original guidance, to 24,000 to 26,000
ounces.
production in the first nine months of 2019 was 19,138 ounces. Due to
issues around mine development and stope availability in Q3, the Company
expects fourth quarter production to be in the range of 5,000 to 7,000
ounces. Accordingly, full year 2019 production guidance has been
adjusted from 39,200 ounces per original guidance, to 24,000 to 26,000
ounces.
While operating costs were stabilized
in Q3, as a result of lower production for the year and higher costs in
the first half, annual AISC guidance has been modified and is expected
to be in the range of US$2,000 to US$2,200 per ounce, from original
guidance of US$1,300 to US$1,350 per ounce. Further information on
operating costs will be provided when the Company files its Q3
financials.
in Q3, as a result of lower production for the year and higher costs in
the first half, annual AISC guidance has been modified and is expected
to be in the range of US$2,000 to US$2,200 per ounce, from original
guidance of US$1,300 to US$1,350 per ounce. Further information on
operating costs will be provided when the Company files its Q3
financials.
2020 Life of Mine Plan and Financial Budget
The
Company is currently updating its life of mine plan and preparing a
2020 budget. The Company will provide further guidance for 2020 at that
time.
Company is currently updating its life of mine plan and preparing a
2020 budget. The Company will provide further guidance for 2020 at that
time.
For further information, please contact:
Stephen G. Roman
Chairman and Interim CEO
Tel: 416-368-0999
Email: sgr@hartegold.com
Stephen G. Roman
Chairman and Interim CEO
Tel: 416-368-0999
Email: sgr@hartegold.com
x