International Tower Hill (ITH.to) (THM): Metallurgy problems, perchance?

This from the company’s news release dated June 29th 2011:

Since December 2010, when major contracts were awarded to carry out its Pre-Feasibility Study, the Company has made significant technical progress and expects the study to be published in the fourth quarter of 2011. Key work programs completed or underway to date include…..Near-completion of metallurgical work programs – including column leaching, gravity concentration and flotation-CIL testing – by FLSmidth, McClelland Labs, RDi, Knelson and Falcon

 This from the company’s news release dated November 22nd, 2011:

While the bulk of engineering studies have been timely completed, a detailed metallurgical review of the Preliminary Economic Assessment flow sheet has indicated further optimization is possible.  The publication date of the PFS is therefore being extended to the first half of 2012.

This from the company’s news release dated today, March 22nd 2012:

While the bulk of engineering studies for the PFS were completed in November 2011, the Company is currently carrying out detailed metallurgical testing after a review of the Preliminary Economic Assessment flow sheet indicated that further optimization is possible.  Due to the large amount of testing underway, the publication date for the PFS is now expected in the third quarter of 2012.

So run that by me again, guys? The met was near complete in June 2011….but then it needed “optimization” (so cute) come November….and then four months later it needed more optimization…..via “large amounts of testing” on things that were near complete eight months ago. Hmmmm….