What? No Copper Fox (CUU.v) feasibility news yet?

Copper Fox (CUU.v) management are liars? Surely not! However, we have now celebrated the end of summer in the Northern hemisphere (10:49am GMT on Sept 22nd is the exact time) and there’s no doubt that CUU.v management has told us on many occasions it would have its feasibility study with us by now:
This NR dated June 14th made it quite clear. Management told us that the feas would be done late summer 2012

“During the quarter, Tetra Tech advised that, due to manpower shortages and scheduling difficulties of staff, the March 31st timeline for completion of the Feasibility Study would not be achieved. The delay in completing the Mine Plan, a critical component in the Feasibility Study, has delayed the completion of the Feasibility Study until mid-late summer, 2012.”

The management’s message was repeated in this NR dated August 2nd which said:

“The feasibility study is being led by Tetra Tech Wardrop on a minimum 120,000 tpd open pit mine and is expected to be completed by late summer, 2012.”

And less than three weeks ago on September 4th, CUU.v confirmed the delivery date of the long awaited feas study:

The feasibility study is being led by Tetra Tech Wardrop on a minimum 120,000 tpd open pit mine and is expected to be completed by late summer, 2012. 

Not to mention the precise same message on September 10th, a mere fourteen days ago! Anyway, here’s a  jolly tune to lift the spirits of the idiot myopic sheep long-suffering CUU longs while they wait for their not-scumbag not-misleading not-totalbunchofbullshitter managerial team to come up with the news: